PDC Electrical Contractors assisted in design and and handled the electrical installation for a new Honey Creek Feed Mill. After groundbreaking, construction was slowed by heavy rains over two months. A delay in concrete work pushing steel erection into winter, thereby delaying interior electrical work. The contractor for the steel building was replaced, causing further delays. PDC used extra work hours to get 69 motors installed, 58 tanks wired, and 18,250 feet of conduit installed. The amount of work that had to be done in the cold and at high elevations made the job challenging, but PDC crews pushed through, made their deadlines and started up the mill with no complications.